CHP Sizing for Industrial Sites: A Load Duration Curve Method

A CHP plant that is sized incorrectly at the design stage will underperform for its whole life. Sizing to peak winter demand or to an annual average leaves the engine too big for the site’s heat demand for much of the year. In those hours it either runs at full output and dumps the surplus heat through a radiator, or turns down to match demand and runs at part load, and both reduce the return on the investment. This article sets out a CHP sizing method based on hourly heat demand data.

How to size a CHP plant

Size a CHP plant to the site’s thermal base load, which is the minimum heat demand the site has for most of the year. You find it by building a load duration curve from at least 12 months of hourly heat data. If the engine will run close to full output for most of the year and put almost all of its recovered heat to use, it is the right capacity.

The method has four stages:

  1. Collect half-hourly electricity data, hourly heat data and the temperature each heat load needs.
  2. Build the load duration curve and pick out a few possible engine sizes. Because engines are rated by electrical output, use the heat-to-power ratio to convert each heat output into an electrical rating.
  3. Check each size for run hours, heat utilisation and part-load performance.
  4. Decide whether to install one large engine or several smaller ones.

How to build and use a load duration curve

Take a year of hourly heat demand and sort the 8,760 values from highest to lowest. The curve shows how many hours each output level is needed, so the base load points to the capacity that can run continuously. Temperature shapes how much of that demand an engine can serve, since jacket-water and lube-oil heat suits LTHW systems while process steam can only come from the exhaust via a waste heat boiler.

Draw a horizontal line at any candidate thermal output. Where it meets the curve gives the hours per year in which demand meets or exceeds that output, and the area beneath the line up to that point is the heat the engine can deliver at full load. An easily missed limitation of the load duration curve is that sorting the data removes the time order. Heat and power demand can therefore peak at different hours even when their curves look compatible. Check each possible engine size against the original hourly data before committing to it.

Worked example: three candidate sizes

Every figure here is hypothetical. A site with continuous process heat and seasonal space heating peaks at 3.0 MWth; its curve shows 1.2 MWth present for around 8,000 hours a year, 1.8 MWth for around 5,000 and 2.4 MWth for around 2,000. Assume a 1:1 heat-to-power ratio and roughly 8,000 available hours after maintenance.

CandidateThermal output (MWth)Hours at full output, all heat usedRemaining available hours
A1.2~8,000None: demand covers the full year
B1.8~5,000~3,000 at around two-thirds load, or at full load with heat rejected
C2.4~2,000~6,000 at part load down to half output, or rejecting up to half its heat

Candidate A generates the least electricity, yet every hour it runs is a full-output hour with all of its heat used. B adds 50% more capacity and earns it for about 5,000 hours. C, sized near the winter mean, spends three-quarters of its available hours below rated output, much of it close to its minimum load.

Should CHP be sized to thermal or electrical base load?

For most industrial sites, size to the thermal base load. Exported electricity is usually worth less than the imports it offsets, and heat that is generated but not used undermines the case for the plant. Sizing to the electrical base load is only safe where the engine’s heat output at that size sits below the heat base load, so that all of its recovered heat is absorbed.

Rejected heat lowers the Quality Index, which affects Good Quality CHP status under the CHPQA programme. Exporting surplus electricity has limits too, because generation that runs in parallel with the distribution network must connect under ENA Engineering Recommendation G99. Where the DNO agrees an export limit, a limitation scheme designed to EREC G100 enforces it, and that limit can cap the plant’s useful output whatever the load duration curve suggests.

Oversizing also pushes the plant into part-load running. When an engine runs below rated output, its electrical efficiency falls and more of the fuel energy comes out as heat. For the same heat delivered, the plant makes less electricity, which is the more valuable of its two outputs. Manufacturers specify a minimum continuous load, and an oversized engine will spend long periods close to it. A thermal store, or buffer vessel, reduces this issue. When heat demand drops below the engine’s output, the store absorbs the extra heat, and it releases that heat back when demand rises again. This lets the engine keep running at full output through short dips in demand, which increases its run hours and means it can be sized slightly above the base load.

Two operating factors have the biggest effect on payback: how many hours the engine runs at full output, and how much of its recovered heat the site uses. Maintenance costs often build up per running hour or per kWh generated, so the site pays them whether or not the heat gets used. The spark ratio (electricity price ÷ gas price) shows how much each hour at full output is worth, and it can be worked out from the site’s own tariffs. When the ratio is low, the electricity alone may not cover the running costs, so the plant depends on using its heat in order to pay back.

When is modular CHP better than a single large unit?

Modular, multi-unit CHP is the better fit when the load duration curve has distinct steps, when the site needs to keep generating during maintenance, or when demand is expected to grow. In the worked example, a 1.2 MWth unit covers the base load all year and a second 0.6 MWth unit tracks the 1.8 MWth step for around 5,000 hours. Candidate B, by comparison, would have spent 3,000 of its hours turned down. Splitting the same 1.8 MWth across two units lets the site follow the step in demand so that each engine spends its running hours at or close to full output. The trade-offs are higher capital cost per kW, more engines to maintain and the lower electrical efficiency of smaller units, which need weighing against the part-load hours a single larger engine would run.

With an N+1 configuration and units serviced at different times, the site keeps generating while one engine is offline. Staging lets capacity follow demand as the site grows. The first unit is sized to today’s base load, and further units follow as new process lines, extensions or electrification shift the curve upwards, with the curve rebuilt from the latest hourly data before each stage. Factory-built, containerised modular CHP plants shorten the installation work for each new stage on an operating site. Infrastructure is different: grid connection capacity, gas supply, plant space, flue routes and heat main headers should all be sized for the final build-out so that later units connect without reworking systems the site already depends on.

Sizing checklist

Before approaching suppliers, confirm that:

  • 12 months of hourly heat and half-hourly electricity data are in hand
  • the heat load duration curve is built and the base load read off
  • each candidate has been checked against the hourly series for coincident demand
  • run hours, heat utilisation and part-load hours are known for each size
  • export limits and final build-out infrastructure are agreed